- Release date Sept 1st
- Release ready in QA for testing one month before – August 1st
- We are now on July 15th, 2.5 weeks before the version needs to be ready in QA for testing.
- There are 5 new features in this release:
- FeatureA – takes 5 weeks to develop, 3 weeks already done 2 weeks to go
- FeatureB - takes 3 weeks to develop, development just started few days ago
- FeatureC – Already done
- FeatureD – takes 1.5 to develop. Development hasn’t started yet
- FeatureE – takes 6 weeks to develop, development will end in a week
- The new feature required by the customer will need a week of requirement definition, 3 weeks of development and a week of QA
|